Target

Target - Cottage Grove

Chicago, IL

This project was located at 8560 South Cottage Grove Avenue in Chicago, Illinois and consisted of 3 phases of hot mix asphalt pavement removal and replacement for the parking lot reconstruction. The total grinding area for the removal was 21,907 square yards, and the total hot mix asphalt tonnage for the replacement was 3,890 tons. Full-depth patching and parking lot striping and signage were also included in Gallagher’s scope of work.

Client: Target Corporation
Grinding Area: 21,907 square yards
Hot Mix Asphalt: 3,890 tons