This project was performed for Cook County under trying utility delays. The utilities were supposed to be moved and completed by April 1, 2012, but did not get moved until July 2012. Gallagher reworked their schedule and under acceleration brought the project to the point where only minor items of work need to be completed in 2013.
Client: Cook County
Asphalt: 25,463 tons