Exchange Road

This Illinois Department of Transportation project consisted of 1.5 miles of reconstructing/re-alignment of Exchange Street to improve limited sight distance. The project consisted of phased construction to keep access for the residents and local businesses along with a 180 working day project timeline. Work included storm sewer, box culverts, water main updating, tree removal, earthwork, milling, and HMA full depth pavement.

Client: Illinois Department of Transportation
Tons of Hotmix: 28,200 tons
Tons of Stone: 28,500 tons
Square Yards of Milling: 26,100 square yards
Cubic Yards Excavation: 70,300 cubic yards